Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Duration field derives its default value from Extended settings in the chart configuration when no duration is specified for the task during its creation. It is stored internally and doesn’t have a corresponding custom field in Jira. However, it can be shown on the issue details page by means of Start field and End field specified in the chart configuration.

Please note that duration of tasks cannot be edited in For charts based on the agile scheduling mode, duration is an internal field. Duration of tasks is derived from duration of backlog and sprints they belong to.

Baseline start, Baseline end and Baseline delay fields are only applicable when a baseline is selected.

...

Original estimate correspond to the same system field in Jira when time tracking is enabled in the chart, except for parent tasks in bottom-up mode. In such case, the app calculates Original estimate based on the task’s child issues in the chart rather than the task’s own value in Jira.Work, Spent, Remaining, and Progress fields heavily rely on the chart configuration and may vary significantly depending on the choice of time tracking mode and progress calculation.

Remaining

Remaining field corresponds to the Remaining Estimate field in Jira when time tracking is enabled. Should time tracking not be configured unless progress overrides are used in the chart. In such case, Remaining field can be is calculated based on Progress field or entered manually. In such case, it is saved internally and not sent to Jira.

Spent

Spent field corresponds to the Time Spent field in Jira when time tracking is enabled . Should time tracking not be configured in the chart. Otherwise, Spent field can be is calculated based on Progress field or entered manually.

Work

Work field is calculated as the sum of Spent and Remaining fields when time tracking is enabled. Should time tracking not be configured in the chart, Work can be calculated based on Progress field or entered manually.

Progress

Progress field is calculated based on Spent and Remaining fields. When manual progress calculation based on a custom Jira fields is configured in the chart, Progress can be entered manually and is synced with Jira.Depending on the chart configuration, Work field can be based on dates only and be equal to task duration, or can rely on the combination of Jira fields such as Original estimate, Time spent and Remaining estimate.

To find out more about Work field, please refer to the following page: https://brizoit.atlassian.net/wiki/spaces/GSFJHD/pages/1373045187/Task+duration+calculation+explained#How-exactly-task-work-and-task-duration-are-calculated%3F.

Progress

Depending on the chart configuration, Progress field can be calculated based on Jira fields Time spent and Remaining estimate, can be overridden based on a status, or entered manually. Please note that for parent tasks in bottom-up mode Progress is calculated based on the task’s child issues in the chart, except for when a Progress value for the parent task has be entered manually.

Info

You will see Gantt fields in the table columns, filters and conditional colors stylized as plain text as opposed to Jira fields which use italics.

image-20240515-091300.pngImage Modified