,Gantt Suite lets you track resources the resource workloads and highlights the overloads. Resources panel is located at the bottom of the chart. It shows the list of all resources assignable to chart project(s).

...

Each resource line show resource name, and total assigned workload at the left. The right side shows workload by day/week/month/etc., depending on the selected chart time scale.

...

Resource cell color can be:

  • green - assigned workload is less or equal to resource capacity

  • red - resource is overloaded

Gantt Suite marks a resource as overloaded if number of assigned working hours for a day is bigger than number of working hours specified in chart configuration. This rule does not depend on a selected scale. So, for example, if selected scales is a month and app shows overload - it means a resource has overload in at least one day of the month.

...

Info

Resource workload calculation can slow down chart operations. It is recommended to hide resources when not actually needed, or if you experience a significant slow down.