Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

To view chart without a baseline, clean the selected baseline by clicking the cross to the right of selected baseline.

...

Info

In order to be able to operate with the baselines when task grouping is done, a user would have to create the baseline(s), after the tasks are grouped.

In case a user creates a baseline first, then performs a task grouping, the baselines won’t work as they become irrelevant.