Note

Do you have tasks in your project that act as a parent to another tasks? If yes, please don’t forget to include the field Parent to grouping fields. Skipping it might cause the incorrect display for task duration.

Info

In order to be able to operate with the baselines when task grouping is done, a user would have to create the baseline(s), after the tasks are grouped.

In case a user creates a baseline first, then performs a task grouping, the baselines won’t work as they become irrelevant.