Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

The app supports the nextteam-gen managed projects. Thus, the nextteam-gen managed projects can be added to a chart configuration.

In chart configuration, the nextteam-gen managed projects have the “next-gen” label next to them.

...

Note

When configuring a Gantt chart with the nextteam-gen managed projects please be aware of the limitations that are present, at this time:

  • multiple nextteam-gen managed projects can be added to a chart configuration. Although, only one can be editable at a time

  • mixing the nextteam-gen managed and classic company projects is allowed. Although, some projects will not be editable

  • project is editable only in case the “Task start field” / “Task end field” are added to the screens of the project

...