To highlight a critical path in red click the Show button and tick the checkbox next to “Critical path”:

...

Image Added

Note

Not all the tasks that lay within a critical path may be highlighted in red in case the assignee have different working hours.
You may want to make sure that the tasks within a critical path are assigned to resources that follow chart's main work day schedule.