Company Calendar for Jira v 7.2 x: Concurrence rules for the events that are based on Jira dates

Did you know that you can define the concurrence rules for the events that are based on Jira dates sources?

To do that, open a Jira dates source configuration and select one of the options.

By default, concurrent events are allowed.

“Don't allow concurrent events” means that no concurrent events are allowed.

“Don't allow concurrent events on assignee level” means that concurrent events are allowed as long as the events' assignees differ.

Please note that events created via the Jira “Create issue” dialog will not comply with the concurrence rules defined in the calendar configuration.