Creating a dependency
Creating a dependency
A dependency between two tasks can be created by:
Drawing a link between tasks.
Right-clicking a task and selecting Dependencies from the context menu.
Drawing a link
To create a dependency (link) between tasks, hover over the source task and click the linking circle.
|
---|
Then, drag it to the start or end of the target task until it fills with color, and release the mouse button.
|
---|
The result is as follows: Once the linking is complete, Gantt Suite moves the second task as close to the end of the first task as possible, provided that no constraints are present.
|
---|
From context menu
Right-click the task and select Dependencies from the context menu.
Click Dependencies.
|
---|
Select the task to link with. Add lag or lead if needed. Click Add.
Select the task to link with. Add lag or lead if needed. Click Add.
|
---|
|
---|
, multiple selections available,
Related content
Task markers, Flags
Task markers, Flags
Read with this
Gantt Suite for Jira v 2.2.x: Creating a task dependency
Gantt Suite for Jira v 2.2.x: Creating a task dependency
More like this
Working with resources
Working with resources
Read with this
Gantt Suite for Jira v 3.0.x: Creating a task dependency
Gantt Suite for Jira v 3.0.x: Creating a task dependency
More like this
Setting task duration
Setting task duration
Read with this
Gantt Suite for Jira v 5.0.x: Creating a task dependency
Gantt Suite for Jira v 5.0.x: Creating a task dependency
More like this