Creating a dependency
Create dependencies between tasks to define the order in which work should be performed. Gantt Suite supports two ways of creating task dependencies:
Drawing a link directly on the timeline.
Using the Dependencies option in the task context menu.
Method 1: Draw a dependency
This is the quickest way to create a dependency between two tasks.
To create a dependency:
Hover over the source task on the timeline.
Click the link handle (the small circle that appears on the task bar).
|
|---|
Drag the link to the start or end of the target task.
When the target connection point is highlighted, release the mouse button.
|
|---|
The dependency is created immediately.
If Auto-scheduling is enabled, Gantt Suite automatically adjusts the successor task so that it is scheduled as close as possible to the predecessor while respecting existing scheduling constraints.
|
|---|
Method 2: Use the context menu
Use this method when you want to specify additional dependency settings, such as lag or lead.
To create a dependency:
Right-click the task.
Select Dependencies from the context menu.
Click Dependencies.
|
|---|
Select:
the task to link,
the dependency type,
an optional Lag or Lead value.
Click Add.
Select the task to link with. Add lag or lead if needed. Click Add.
|
|---|
|
|---|
The dependency is added to the chart.
Lag and Lead
When creating a dependency, you can specify an offset between the predecessor and successor tasks.
Lag delays the successor task after the dependency is satisfied.
Lead allows the successor task to start before the predecessor relationship is fully completed.
For example:
FS +2d – the successor starts 2 working days after the predecessor finishes.
FS -1d (Lead) – the successor starts 1 working day before the predecessor finishes.
Best practices
Use drag-and-drop when creating simple dependencies quickly.
Use the Dependencies dialog when you need to specify the dependency type, lag, or lead.
Prefer Finish-to-Start (FS) dependencies unless another relationship better reflects your project's workflow.
Avoid creating unnecessary dependency chains, as they can make schedules more difficult to maintain.
Enable Auto-scheduling to automatically update dependent tasks whenever a predecessor changes.