Creating a dependency

Creating a dependency

Create dependencies between tasks to define the order in which work should be performed. Gantt Suite supports two ways of creating task dependencies:

  • Drawing a link directly on the timeline.

  • Using the Dependencies option in the task context menu.


Method 1: Draw a dependency

This is the quickest way to create a dependency between two tasks.

To create a dependency:

  1. Hover over the source task on the timeline.

  2. Click the link handle (the small circle that appears on the task bar).

 

Screenshot 2025-01-30 at 13.29.57.png

 

 

Screenshot 2025-01-30 at 13.29.57.png

 

  1. Drag the link to the start or end of the target task.

  2. When the target connection point is highlighted, release the mouse button.

 

Screenshot 2025-01-30 at 13.30.53.png

 

 

Screenshot 2025-01-30 at 13.30.53.png

 

The dependency is created immediately.

If Auto-scheduling is enabled, Gantt Suite automatically adjusts the successor task so that it is scheduled as close as possible to the predecessor while respecting existing scheduling constraints.

 

Screenshot 2025-01-30 at 13.38.45.png

 

 

Screenshot 2025-01-30 at 13.38.45.png

 

 

Method 2: Use the context menu

Use this method when you want to specify additional dependency settings, such as lag or lead.

To create a dependency:

  1. Right-click the task.

  2. Select Dependencies from the context menu.

 

Screenshot 2025-01-30 at 13.45.11.png
Click Dependencies.

 

 

Screenshot 2025-01-30 at 13.45.11.png
Click Dependencies.

 

  1. Select:

  • the task to link,

  • the dependency type,

  • an optional Lag or Lead value.

  1. Click Add.

 

Screenshot 2025-01-30 at 13.46.15.png
Select the task to link with. Add lag or lead if needed. Click Add.

 

 

Screenshot 2025-01-30 at 13.46.15.png
Select the task to link with. Add lag or lead if needed. Click Add.

 

 

Screenshot 2025-01-30 at 13.57.57.png

 

 

Screenshot 2025-01-30 at 13.57.57.png

 

The dependency is added to the chart.


Lag and Lead

When creating a dependency, you can specify an offset between the predecessor and successor tasks.

  • Lag delays the successor task after the dependency is satisfied.

  • Lead allows the successor task to start before the predecessor relationship is fully completed.

For example:

  • FS +2d – the successor starts 2 working days after the predecessor finishes.

  • FS -1d (Lead) – the successor starts 1 working day before the predecessor finishes.


Best practices

  • Use drag-and-drop when creating simple dependencies quickly.

  • Use the Dependencies dialog when you need to specify the dependency type, lag, or lead.

  • Prefer Finish-to-Start (FS) dependencies unless another relationship better reflects your project's workflow.

  • Avoid creating unnecessary dependency chains, as they can make schedules more difficult to maintain.

  • Enable Auto-scheduling to automatically update dependent tasks whenever a predecessor changes.