Gantt Suite for Jira v 1.12.x Using the same task in multiple charts

If a task is used in two or more charts (including other user’s charts), and the Task start field is the same for those charts, then moving task in one chart will move the task on all other charts.

In order to make tasks independent of other charts, make sure each chart has a unique setting for Task start field Scope ).

 

If a task is used in two or more charts, then changing task duration in one chart will set the same duration on all other charts. This behavior is hard-coded and can’t be customized.