Gantt Suite for Jira v 1.12.x Known Issues and Limitations

Time zone settings recommendations

In order for Gantt Suite to work correctly the time zone set on user's PC has to match the time zone set in user's Jira profile.

In case, user has selected "Only you" for his/her time zone visibility, in Jira profile, the time zone set on user's PC has to match the default time zone set in Jira settings:

Administration > System > Default user time zone

Next-gen projects aren't yet supported

Next-gen projects aren't yet supported by Gantt Suite. The feature is planned for future release.

Internet Explorer 11 is not supported

Gantt Suite is tested for compatibility with the following browsers:

  • Google Chrome
  • Firefox
  • Microsoft Edge

Explorer 11 is no more supported.

Task end time is rounded to closest working time

If task ends on weekend, and weekend is not marked as a business day, then task end time will be moved to the last working hour of a day that comes before the weekend. This is not a defect as it doesn't affect task duration in any way.

Sharing tasks between multiple charts

If a task is used in two or more charts, and the Task start field is set the same for those charts, then moving task in one chart will move the task on other charts.

In order to make tasks independent of other charts, make sure each chart has unique setting for Task start field Gantt Suite for Jira v 1.12.x Scope ).

The task duration is also shared between multiple charts. Gantt Suite saves duration into Jira's Time tracking field. So changing a task duration will result in this task duration being changed in all other charts. Unfortunately, it is not currently possible to change this behavior.