Gantt Suite for Jira v 2.1.x: Toolbar

 

View/edit chart configuration

 

Chart home page/ list of charts

 

Refresh chart

 

Expand / collapse all tasks

 

Show or hide tasks grid (https://brizoit.atlassian.net/wiki/spaces/GSFJHD/pages/3186328477, left-side panel). Select columns for the left-side grid.

 

Users can select which fields they want to be shown as columns on the left-side grid. In addition, they can achieve the desired column order by drag-and-dropping selected fields in the dialog.

On exported to Excel chart, besides default standard fields, the additionally selected fields will be shown. Extra fields will not be shown on a chart shared with the public via URL or as embedded.

 

Create and add a new task to the chart

 

Save parent task data to Jira

Use this button in case you want to update the Jira dates for parent tasks based on the dates that are displayed for parent tasks, on a chart.

 

Group tasks by selected Jira fields / Create chart hierarchy

Please note that you can now edit parent tasks. For such tasks can only edit summary and assignee. Other properties are calculated from children

Hide tasks that don’t match search criteria

 

Task search results may or may not include the task-children, depending on your preferences. To include the task-children to search results, simply, tick the checkbox within Search.

 

Filter tasks by assignees

 

Filter tasks by issue type

 

Filter tasks by issue status

 

Scroll to current date

 

 

^^^ Tasks grid ON

^^^ Tasks grid OFF

Show or hide resources (https://brizoit.atlassian.net/wiki/spaces/GSFJHD/pages/3186328596, bottom panel)

^^^ Resources ON

^^^ Resources OFF

Toggle visibility of the elements on a chart:

Tasks on critical path are highlighted in red when show critical path is selected

Show or hide Today and release markers (vertical orange lines on the today’s date and release dates)

Show or hide issue key and summary to the right of the task bar

Show or hide assignee/workload to the left of the task bar*

Show tasks, according to chart JQL order

 

Set timeline and resources scale. Timeline and resources cell range will change depending on a selected scale.

 

Hour scale allows to set duration in minutes

Day scale allows to set duration in hours. Non-working days are marked with gray background.

Other scales allow to set duration in days

 

 

 

Select or create a baseline for the chart. Details: https://brizoit.atlassian.net/wiki/spaces/GSFJHD/pages/3186329088