Task deadline

Task deadline

A task deadline can be set via task edit dialog (double-click the task or select Edit from the task context menu).

image-20251002-102413.png

 

image-20251002-102413.png

 

Once a deadline is set, it is shown as a green arrow at the end of the deadline day.

image-20251002-102531.png

 

image-20251002-102531.png

 

In case a task deadline is failed, the red exclamation mark gets shown in the Flags column.

image-20251002-102603.png

 

image-20251002-102603.png

 

The deadline feature is only available if configured in chart settings (“Task deadline field” is selected in chart settings)