Team assignment
Starting with the app version 3.0, a team assignment can be used when it comes to the resource management. Please use the instructions below to make a team assignment available in your Gantt chart.
First, open your chart configuration on Resources tab.
|
Then, select a field to store a team assignment.
Note that the Team assignment field has to be a custom field with the type of Short text (plain text only) in case you are working in cloud Jira or Text Field (single line) in case you are working in server Jira.
In cloud Jira, the field must be added to the screens of project(s) configured for Gantt chart.
A task can be assigned either to a resource, a team, or both. When a field is selected, the field "Team" will be available on the Edit task dialog.
Once a field to store a team assignment is selected, click Save.
Next, click the button Teams to start creating teams.
|
Then, click the Add Team button.
|
Next, provide a team name, check the Associate checkbox if needed, provide the team capacity in hours, and click Save.
Note that only the teams that are associated with the Gantt chart will be available for a team assignment for a given chart.
|
In the next step, you may want to define the team members. Simply, click the Team members button to start configuring a team membership.
|
One by one, select the team members and click Save.