Gantt Suite for Jira v 2.2.x: Setting task duration
Gantt Suite for Jira v 2.2.x: Setting task duration
A task duration can be set in the following ways:
Drag the left or right end of the task using mouse, and release when done.
Double click the task bar or task in leftside grid. This will open task edit dialog. Set desired duration and click Save.