Gantt Suite for Jira v 2.2.x: Task duration calculation explained
Gantt Suite for Jira v 2.2.x: Task duration calculation explained
Task duration is calculated using worktime only. Non-working time is excluded.
Non-working time is:
days marked as non-working
hours marked as non-working
Consider the following tasks: