Agile scheduling. Planning by sprint.

Agile scheduling. Planning by sprint.

Starting the app version 3.0, planning by sprint is available thanks to Agile scheduling.

image-20251002-095524.png

 

 

Unlike in Standard scheduling, you would have to select the project board(s) instead of project(s) in chart configuration.

The task start/end fields are not configured as the task start/end dates are defined by a sprint a task belongs to.

image-20251002-095605.png

 

On Gantt chart with Agile scheduling, the sprint markers are shown.

image-20251002-095634.png

 

If needed, the sprint marker display can be removed from a chart view via User settings.

image-20251002-095833.png

 

 

When planning by sprint, a user is able to move task to a sprint either via right click on a task or the Actions column.

image-20251002-095857.png

A task can be moved only to an active or future sprint.