Published May 15, 2024
Gantt Suite for Jira v 4.0.x: Using the same task in multiple charts
If a task is used in two or more charts (including other user’s charts), and the Task start field is the same for those charts, then moving task in one chart will move the task on all other charts.
In order to make tasks independent of other charts, make sure each chart has a unique setting for Task start field ( Scope ).
If a task is used in two or more charts, then changing task duration in one chart will set the same duration on all other charts. This behavior is hard-coded and can’t be customized.
Looking for labels? They can now be found in the details panel on the floating action bar.
Related content
Gantt Suite for Jira v 2.0.x: Using the same task in multiple charts
Gantt Suite for Jira v 2.0.x: Using the same task in multiple charts
More like this
Gantt Suite for Jira v 3.0.x: Using the same task in multiple charts
Gantt Suite for Jira v 3.0.x: Using the same task in multiple charts
More like this
Gantt Suite for Jira v 2.1.x: Using the same task in multiple charts
Gantt Suite for Jira v 2.1.x: Using the same task in multiple charts
More like this
Gantt Suite for Jira v 2.2.x: Using the same task in multiple charts
Gantt Suite for Jira v 2.2.x: Using the same task in multiple charts
More like this
Gantt Suite for Jira v 5.0.x: Using the same task in multiple charts
Gantt Suite for Jira v 5.0.x: Using the same task in multiple charts
More like this
Gantt Suite for Jira v 6.0.x: Using the same task in multiple charts
Gantt Suite for Jira v 6.0.x: Using the same task in multiple charts
More like this