Gantt Suite for Jira v 9.0.x: Known Issues and Limitations
Time zone settings recommendations
In order for Gantt Suite to work correctly the time zone set on user's PC has to match the time zone set in user's Jira profile.
In case, user has selected "Only you" for his/her time zone visibility, in Jira profile, the time zone set on user's PC has to match the default time zone set in Jira settings:
Administration > System > Default user time zone
Issue limit per chart
The issue limit for a chart is:
in cloud version, 5000
in DC version, 10000
As a result, some of the issues or projects could be missing from a loaded chart. You might want to apply JQL in the chart configuration to see all relevant issues.
Task end time is rounded to closest working time
If task ends on weekend, and weekend is not marked as a business day, then task end time will be moved to the last working hour of a day that comes before the weekend. This is not a defect as it doesn't affect task duration in any way.
Sharing tasks between multiple charts
If a task is used in two or more charts, and the Task start field is set the same for those charts, then moving task in one chart will move the task on other charts.
In order to make tasks independent of other charts, make sure each chart has unique setting for Task start field ( Scope ).
The task duration is also shared between multiple charts. Gantt Suite saves duration into Jira's Time tracking field. So changing a task duration will result in this task duration being changed in all other charts. Unfortunately, it is not currently possible to change this behavior.
Chart loading for a chart that is configured with a scheduling mode by task end
We strongly recommend you to use the scheduling mode by task start as scheduling by task end may significantly slow down a chart generation. In the near future, the by task end mode will be obsolete.
If scheduling mode is set by task end, planning by whole days is strongly recommended. Planning in hours and minutes may lead to incorrect app behavior.
If scheduling mode by task start is not suitable for your business case, you may want to apply a JQL to a chart configuration in order to narrow the chart’s scope. Thus, improve a chart loading. Chart’s scope configuration is described in details here.
The example of JQL that is applied to a chart configuration is shown below: