As user I want to see a task delay, in the left-side grid, based on created baseline

Description

As the customer suggested during the meeting, it would be nice for an app user to see the task delays in the left-side grid columns.
Since multiple baselines can be created for one chart, suggesting to show a delay based on currently selected baseline.

In addition, we may want to show a delay information in regards to date changes, once a user hovers over the initial task position (baseline position).

To be further discussed.

Attachments

3
  • 23 Feb 2024, 12:19 pm
  • 09 Feb 2022, 02:40 pm
  • 09 Feb 2022, 02:39 pm

Activity

Show:

Oksana Kostolovych 23 February 2024 at 12:25
Edited

The enhancements agreed upon based on today’s team discussion:
1. From now on, we do not save any dates for unscheduled tasks, and thus do not store any baseline dates and delays for them;
2. If a task was ones scheduled and a baseline saved for it, but later the task’s dates were cleared (this refers to old unscheduled tasks, too, since we previously saved dates for them):
- we keep the baseline data;
- however, we do not show any delays for such tasks.

Oksana Kostolovych 23 February 2024 at 12:19

The delay is shown in the table column for the tasks but not for the project level:

Sviatoslav Dubyniak 19 February 2024 at 11:53

We agreed to only display the delay for the task. If the end date precedes the planned end day in the baseline, we show nothing to avoid distracting the user, as we do during task dragging and tooltip display.

Yuriy Harbuziuk 6 September 2023 at 12:10

In this Delay column we could show positive and negative values. Positive when task is delayed, negative when task gets finished earlier than baseline.

Details

Assignee

Reporter

Labels

App Type

Cloud
DC

Version

QA Passed for

Cloud
Server

Time tracking

1d 2h 5m logged4h 15m remaining

Fix versions

Priority

Created 9 February 2022 at 14:40
Updated 31 January 2025 at 13:07