Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

App configuration is accessible from Jira settings → Apps → Gantt Suite → Configuration:

...

Gantt settings

...

Gantt settings, defined in Gantt Suite configuration, are the default values only for the new charts. Existing charts aren’t affected by the changes.

Here, administrator can select the default scheduling mode for the charts, either task start or task end.

  • Task start field defines a Jira field to use to store Gantt Suite custom information. Gantt Suite will try to create and pre-select a Jira custom field named Start Date [Gantt].
    In order for app to work correctly, the field must be added to Jira screens on projects where app will be used. See Scope for more info how this field will be used.

Calendar

...

Info

If scheduling mode is set by task end, planning for whole days is strongly recommended. Planning in hours and minutes will lead to incorrect app behavior.

Calendar

...

Here, administrator can set the default values for the new charts in regards to working days and hours. Existing charts aren’t affected by changes.

...

Allow impersonated view is NOT a default value. It affects all charts, existing and new ones. It The option is only visible to Jira administrators.

Normally, users without permissions to access projects or issues will not see them on a chart eitherneither. This option lets chart creators to allow users with restricted access to see the tasks on a chart in view-only mode. In other words, it allows users with restricted access to see chart the way chart owner does.

When this company-wide option is turned on and chart creator also turned impersonation on, app impersonates as chart creator for Jira issues and links loading. All other operations are NOT using impersonation.

Links configuration

...

These are The values defined here by administrator are the default values only for the new charts. Existing charts aren’t affected by changes.

...