Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Expand / collapse all tasks

Show or hide tasks grid (Task grid, left-side panel). Select columns for the left-side grid.

...

Toggle visibility of the elements on a chart (Show button):

...

...


Show or hide tasks grid (https://brizoit.atlassian.net/wiki/spaces/GSFJHD/pages/1373045090, left-side grid)

Show or hide the timeline (bars and links area)

Tasks on critical path are highlighted in red when show critical path is selected

...

Show or hide issue key and summary to the right of the task bar

Show or hide assigneeresource/workload to the left of the task bar*

Show tasks, according to chart JQL order

Info

*Note that assignee workload % for a task is shown in case the task work and task duration differ.

...

When Constant display of milestones is marked, milestones will be shown on parent tasks too (will roll up). This allows to see milestones on top levels even if the whole tree is collapsed. In example below, the milestone is shown on a collapsed project because Constant display of milestones is marked.

...

Show tasks sorted by a grid column, or sorted according to order defined in the chart JQL

Tip

Did you know you can set the initial task order according to chart JQL order even though you may have reordered the tasks on a chart?

Assuming there is an ‘order by’ clause in chart JQL, you can reset the tasks according to the JQL provided in chart configuration. Simply click Initial task order by chart JQL under Show menu.

...