Did you know you can use Gantt chart with deactivated Jira time tracking? On tab Task progress, simply, select the option “No time tracking“.

Image Removed

Note

For server app version, in case Jira time tracking is deactivated, a chart manager won’t be able to select the option “Time tracking“ on the tab Task progress as the validation error will go into affect.

Jira time tracking

Most likely, the most common option to be used for a task progress is Jira time tracking.

...

Tip

The option Custom estimate field can be used even in case Jira time tracking is deactivated in Jira.

No time tracking

Did you know you can use Gantt chart with deactivated Jira time tracking? On tab Task progress, simply, select the option “No time tracking“.

Image Added

Note

For server app version, in case Jira time tracking is deactivated, a chart manager won’t be able to select the option “Time tracking“ on the tab Task progress as the validation error will go into affect.

The task progress, in such case, is calculated either by:

  • status

  • or, manual

Manual task progress calculation

The manual task progress calculation is accessible in all time tracking modes.

You would have to select a custom field with the type of Number field to be used in task progress calculation.

Image Added