No time tracking
Did you know you can use Gantt chart with deactivated Jira time tracking? On tab Task progress, simply, select the option “No time tracking“.
Note |
---|
For server app version, in case Jira time tracking is deactivated, a chart manager won’t be able to select the option “Time tracking“ on the tab Task progress as the validation error will go into affect. |
Jira time tracking
Most likely, the most common option to be used for a task progress is Jira time tracking.
...
Info |
---|
This common behavior can be overridden by applying the progress overrides. |
Use case #1. Your company doesn't set zero as remaining estimate on Done tasks, so Done tasks are shown with progress less than 100%.
Solution: add an override for status Done and set 100 as percent value. All tasks in status Done will have 100% regardless time spent.
...
In case a parent task has Manual mode, the progress override will apply to the parent task. Please see an example below.
Custom estimate field
Another option to be used for a task is progress is called Custom estimate field, and it comes handy in case a team s operating with such fields as Story point estimate or Story Points.
When it comes to a task progress calculation, similarly, as with the option Time tracking, it can be calculated either by:
estimate
estimate and status
status
or, manual
Tip |
---|
The option Custom estimate field can be used even in case Jira time tracking is deactivated in Jira. |
No time tracking
Did you know you can use Gantt chart with deactivated Jira time tracking? On tab Task progress, simply, select the option “No time tracking“.
Note |
---|
For server app version, in case Jira time tracking is deactivated, a chart manager won’t be able to select the option “Time tracking“ on the tab Task progress as the validation error will go into affect. |
The task progress, in such case, is calculated either by:
status
or, manual
Manual task progress calculation
The manual task progress calculation is accessible in all time tracking modes.
You would have to select a custom field with the type of Number field to be used in task progress calculation.
Once a manual task progress calculation is configured, the relevant field will be shown on edit task dialog.
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Quick tip: To avoid the error messages, make sure the custom field used for a manual task progress calculation is added to the screens of configured project(s). |