To add a resource calendar to a chart configuration, first, open the Calendar(s) Resources tab, in chart configuration.

...

Then, click the Add button, on the right.

Image Modified

Select a resource, and click the Create button.

...

Image Added

Info

Note that the about to be added resource calendar contains the working hours and overrides taken from the main chart calendar.

...

These can be changed according to the resource work schedule requirements, and ,therefore, differ from the main work schedule.

For instance, in case you want to add a vacation time for the resource, click the field Override as non-business day. Then, select the start and end date of the planned vacation.

...

Image Added

Once the date range is selected, click the Add button. Then, click Save button.

...

Image Added

The vacation time will be shown underneath:

...

Image Added

Tip

In case a single date has to be added as a non-working day for the selected resource, double click the same date on a calendar.

Note

The important step is to click the Save button below. Without it, the resource calendar will not be created, and any changes made to a calendar will not be finalized.

...

Image Added

To see the configured calendars, including the main chart calendar, click the field under the Calendar Scope.

...

Image Added

The main chart calendar is, simply, called Chart.

To delete an existing resource calendar, select the resource calendar, first, in the Calendar Scope.

Image Modified

Then, click the Delete button.

...

Confirm the action by clicking the OK button.

...

Note

Important: to make the changes final click the Save button below.

...