Gantt Suite for Jira v 2.1.x: Toolbar
Â
View/edit chart configuration
Â
Chart home page/ list of charts
Â
Refresh chart
Â
Expand / collapse all tasks
Â
Show or hide tasks grid (Gantt Suite for Jira v 2.1.x: Task grid, left-side panel). Select columns for the left-side grid.
Â
Users can select which fields they want to be shown as columns on the left-side grid. In addition, they can achieve the desired column order by drag-and-dropping selected fields in the dialog.
On exported to Excel chart, besides default standard fields, the additionally selected fields will be shown. Extra fields will not be shown on a chart shared with the public via URL or as embedded.
Â
Create and add a new task to the chart
Â
Save parent task data to Jira
Use this button in case you want to update the Jira dates for parent tasks based on the dates that are displayed for parent tasks, on a chart.
Â
Group tasks by selected Jira fields / Create chart hierarchy
Please note that you can now edit parent tasks. For such tasks can only edit summary and assignee. Other properties are calculated from children
Hide tasks that don’t match search criteria
Â
Task search results may or may not include the task-children, depending on your preferences. To include the task-children to search results, simply, tick the checkbox within Search.
Â
Filter tasks by assignees
Â
Filter tasks by issue type
Â
Filter tasks by issue status
Â
Scroll to current date
Â
Â
^^^ Tasks grid ON
^^^ Tasks grid OFF
Show or hide resources (Gantt Suite for Jira v 2.1.x: Resources, bottom panel)
^^^ Resources ON
^^^ Resources OFF
Toggle visibility of the elements on a chart:
Tasks on critical path are highlighted in red when show critical path is selected
Show or hide Today and release markers (vertical orange lines on the today’s date and release dates)
Show or hide issue key and summary to the right of the task bar
Show or hide assignee/workload to the left of the task bar*
Show tasks, according to chart JQL order
Â
Set timeline and resources scale. Timeline and resources cell range will change depending on a selected scale.
Â
Hour scale allows to set duration in minutes
Day scale allows to set duration in hours. Non-working days are marked with gray background.
Other scales allow to set duration in days
Â
Â
Â
Select or create a baseline for the chart. Details: Gantt Suite for Jira v 2.1.x: Working with baselines