Gantt Suite for Jira v 4.0.x: Timeline (Gantt chart)
 |
The timeline visualizes Jira projects / issues as Gantt chart elements. Initially, timeline shows projects (summary tasks), tasks including progress line, and task dependencies (links). It allows to manage the tasks and their dependencies. For more details, see Gantt Suite for Jira v 4.0.x: Working with tasks.
To drag the timeline left or right click and hold mouse button while moving mouse left or right.
User can enable following elements on timeline:
baseline (orange). For more details, see Gantt Suite for Jira v 4.0.x: Working with baselines .
critical path (red)
today and release markers (vertical lines)
task assignee to the left of a task bar
task summary to the right of a task bar
Time scale at the top of the timeline changes according to the selected scale.
Starting the app version 2.2.x, the users can enable the task deadline display (green arrow pointing down) by configuring the Deadline field in chart configuration Gantt Suite for Jira v 4.0.x: Chart settings tab
 |
Also, starting the app version 2.2.x, the app users can easily convert task to a milestone (purple) and vice versa, simply, by hovering over a task and right clicking and then selecting the option, s shown below.
 |
 |
 |