Gantt Suite for Jira v 3.0.x: Resources tab
The resource configuration set by an admin will be auto-populated on this tab. Although, a chart manager will be able to override the global defaults.
Here, you can define the work time for your team in general and as per individual resource by adding and configuring individual resource calendars.
In addition, as a chart manager, you’ll be able to configure the field for resource assignment.
By default, standard Jira field Assignee is used for a resource assignment. Although, any custom field with the type of User picker (single user) can be used for a resource assignment.
 |
 |
If needed, the Resource panel can be hidden from Gantt chart display by unticking the Resource panel checkbox.
 |
Starting the app version 3.0.x, the Gantt Suite teams are available.
In order to use a team assignment in Gantt chart, the field with the type of Short text (plain text only) has to be selected.
 |
Then, the teams have to be created and associated with the Gantt chart. This can be done by clicking the button Teams.
 |
More information regarding the team assignment can be found here: Team assignment.